Consulting and Supervisory Services for the Phase 3 of the Expansion of Sarcheshmeh Concentrate Plant

Based on the contract, consulting and supervisory services for three projects were provided:

  1. EPC for the copper concentrator plant (expansion Phase 3) with the feed capacity of 4,000 tons per hour

This project, after delivering a considerable amount of engineering services, and procurement of some equipment, was halted based on its employer’s decision.

  1. EPC for the molybdenum dewatering plant with the capacity of 90 tons per day

This project was carried out as part of the phase 3 of the expansion plan of Sarcheshmeh Concentrator Plant, and for the following reasons:

  • Insufficiency of the initial capacity for receiving the produced molybdenum concentrate from Phases 0, 1, and 2 of the expansion of Sarcheshmeh Concentrator Plant
  • Worn-out equipment and gradual decrease in the rate of efficiency in the old concentrator dewatering and drying units
  • The urge for using state-of-the-art technology in dewatering process
  • Predictions and considerations for future developments of the concentrator plant
    1. Construction of reject crusher in the circuit of the Semi-Autogenous Mill (SAG Mill) in Phase 1 of the concentrator plant expansion

The purpose of the project was to increase the efficiency of the SAG Mill circuit in the Phase 1 of Sarcheshmeh Concentrator Plant expansion plan.